A proposed micro hydro scheme with a gross head of 50 meters is proposed to meet the following demands as an alternative to a diesel powered mill and a generator which costs around \$0.05 per kWh of energy. Provided that the minimum flow of $160 \text{ l/s}$ is available during winter from Kartik to Chaitra while it does not fall less than $200 \text{ l/s}$ from Baishakh to Ashwin, will there be enough water to satisfy the irrigation demand together with lighting and milling demand? If yes, decide whether the proposed hydro scheme is viable if the annual cost of capital repayment is \$ 6,000 and O and M cost is 10% of the annual repayment cost.
| Category | Time | Demand | Duration in year |
|---|---|---|---|
| Lighting | 6 am to 12 am | 40 kW | Round the year |
| Milling | 8 am to 4 pm | 20 kW | Round the year |
| Irrigation | suitable slot | 4000 m³/day | During dry months only |
| Storage Cookers | any time | 3 kW | As per the power availability |
| Battery charging | any time | 1.5 kW | As per the power availability |