2082 BhadraChapter 8: Project Time Management
A Project work consists of the following activities as listed below in table.
| Activity | Duration | Predecessor |
|---|---|---|
| A | 3 | - |
| B | 4 | A |
| C | 5 | A |
| D | 6 | B |
| E | 3 | C |
| F | 2 | C |
| G | 4 | D, E |
| H | 5 | F |
| I | 6 | G, H |