2082 BhadraChapter 8: Project Time Management

A Project work consists of the following activities as listed below in table.

ActivityDurationPredecessor
A3-
B4A
C5A
D6B
E3C
F2C
G4D, E
H5F
I6G, H
Answer the following: a) Draw the network diagram b) Trace critical path with respective activities c) Find out EST, EFT, LST, LFT d) Find Total float of each Activities