A Project work consists of the following activities as listed below in table.
Activity
Duration
Predecessor
A
3
-
B
4
A
C
5
A
D
6
B
E
3
C
F
2
C
G
4
D, E
H
5
F
I
6
G, H
Answer the following: a) Draw the network diagram b) Trace critical path with respective activities c) Find out EST, EFT, LST, LFT d) Find Total float of each Activities