Project Management
CT 701
Question
2082 BaishakhChapter 8: Project Time Management
The discussion among investors of a company to explore new avenue with manufacturing gift items/merchandise targeted for various events. You are assigned as the project manager of this pilot project. Your team has come up with the following associated activities and timings.
| Activity | Description | Predecessor | Time (In number of days) | ||
|---|---|---|---|---|---|
| Optimistic | Most Likely | Pessimistic | |||
| A | Design package | None | 8 | 15 | 22 |
| B | Design product | A | 21 | 25 | 35 |
| C | Secure patent | B | 30 | 45 | 60 |
| D | Build package | A | 6 | 9 | 12 |
| E | Build product | B | 30 | 36 | 48 |
| F | Finishing and detailing | C, D, E | 9 | 12 | 15 |
| G | Run pilot campaign | F | 5 | 7 | 9 |
Add an answerChecking contribution access...