2069 ChaitraChapter 3: Power and Energy Potential study3.1 Processing of hydrological data, Use of extreme and long term hydrological data, mass and elevation volume curves, flow duration curves

The stream flow record for a hydropower development site is given below. Draw a flow duration curve and determine firm and secondary energy if the available head is 60 m, design discharge capacity is 45 m³/s, and overall efficiency is 82%. [8]

Months Jan Feb Mar Apr May Jun July Aug Sept Oct Nov Dec
Q (m³/s) 30 38 28 22 16 32 56 72 54 46 38 36