CE 704 · Chapter 4

Hydropower Engineering past question

4.3.1 General arrangement of Intakes for storage plants, Location, Hydraulics of intake

Design and draw section of a side intake with coarse trash racks for a project in which river bed level is 3315.0 m amsl. Weir crest level is fixed to 3317.5 m amsl. The highest flood level in 100 years return period is 3320.83 m amsl and flood level in 20 years return period is 3319.55 m amsl. The canal water level is fixed at 3317.5 m amsl. The design discharge is 1.45 m³/se. Assume other suitable data. [6]