CE 704 · Chapter 6
Hydropower Engineering past question
6.2 Forebay and Surge Tanks: importance, general arrangement, condition of their application, hydraulic design
Design a forebay with following data: Design discharge = 20 m³/s, penstock length = 300 m; Detention line = 3 minutes, diameter of penstock = 2.2 m. [6]