CE 704 · Chapter 3

Hydropower Engineering past question

3.5 Estimation of Power and energy potential

A peaking ROR project in western Nepal with net head of 250m has following river flow data:

Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
River flow (m³/s) 100 80 80 105 200 500 1100 1200 800 350 200 120

The storage capacity available for this project is 1100 million m³. This storage capacity is utilized for dry months (Nov-May) during which the plant is used as peak load plant 4 hours a day. Considering design flow as Q25, calculate maximum power generation (in MW) and ratio of wet season energy to dry season energy. [12]