CE 704 · Chapter 6

Hydropower Engineering past question

6.2 Forebay and Surge Tanks: importance, general arrangement, condition of their application, hydraulic design

Design a fore bay which accommodates a storage for 3 minutes of operation for a hydropower plant having following data: Design discharge = 20 m³/s; Length of penstock = 300 m; Diameter of penstock = 2.20 m. [3]