4.5 Project Cost Control - Earned Value Analysis (EVA)

A construction work had to be completed in 10 days with 50 labor days at Rs 1000 per day i.e., with total cost of Rs 50,000. At the end of third day, only 25% was completed with the use of 18 labor days at Rs 800 per day. Perform EVA and comment on its performance.